New delay to the Fehmarn tunnel: Next immersion postponed
A rubber gasket must be repaired before the tunnel's first special element can be immersed. It is therefore uncertain whether Sund & Bælt will meet this year's target of having six elements in place.
Two elements are still needed before Femern A/S can finalise the new timetable and project budget.
Foto: Sund & Bælt
Four tunnel elements now lie in a row on the seabed off Rødbyhavn. As the contractor prepared to add the fifth to the sequence, divers discovered damage to the leading element.
Buy a subscription and get access
Already a subscriber? Log in here
Personal Subscription
-
Premium access to all content on FemernBusiness
-
Unlimited access to our full archive
-
Newsletters with the most important industry updates
-
Breaking news alerts when the biggest stories happen
-
Website login – stay updated with industry news on the go
Buy subscription
Try FehmarnBusiness for free for 14 days
-
Premium access to all content on FemernBusiness
-
Unlimited access to our full archive
-
Newsletters with the most important industry updates
-
Breaking news alerts when the biggest stories happen
-
Website login – stay updated with industry news on the go
Start free trial