Fourth tunnel element in place: Now comes the harder task
The first almost 900 metres of the Fehmarn Belt tunnel are now in the tunnel trench.
To elementer mangler, før Femern A/S kan gøre den nye tidsplan og projektøkonomi op.
Foto: Sund & Bælt
The fourth tunnel element has been lowered into place south of Lolland. This means that almost 900 metres of the 18-kilometre tunnel to Germany have now been assembled on the seabed.
The first element was put in place in May, the second in June and the third in August. Next time, the special-purpose vessel IVY will have to handle a different type of element: The first of the tunnel’s ten special elements has a basement for technical installations and must be placed deeper than the elements installed so far.
- Each operation is still technically demanding, but we feel well prepared for the next major task, which is the immersion of the first special element with a basement, says Lasse Vester, Deputy Contract Director at Sund & Bælt.
The special element is expected to be immersed in the autumn. It will then be followed by the fifth standard element. Only once all six elements are in place will Sund & Bælt draw up a new overall timetable for the delayed project.
Buy a subscription and get access
Already a subscriber? Log in here
Personal Subscription
-
Premium access to all content on FemernBusiness
-
Unlimited access to our full archive
-
Newsletters with the most important industry updates
-
Breaking news alerts when the biggest stories happen
-
Website login – stay updated with industry news on the go
Buy subscription
Try FehmarnBusiness for free for 14 days
-
Premium access to all content on FemernBusiness
-
Unlimited access to our full archive
-
Newsletters with the most important industry updates
-
Breaking news alerts when the biggest stories happen
-
Website login – stay updated with industry news on the go
Start free trial